Praias de Parajuru WPP

Praias de Parajuru WPP

Eólica

 

Start of Construction

2009

Start of Operations

2009

Nominal Wind Speed

11m/s

Wind Turbine Height

85m

Installed Power

28,8MW

Generating Units

19

Learn more about it

Praias de Parajuru Wind Power Plant consists of 19 wind turbines, with a total installed power of 28.8 MW. The equipment is manufactured by the German company Vensys, model VS77, with permanent magnet synchronous multipole generator and unit power of 1,540 kVA, nominal output voltage of 690 Volts, operating with nominal wind speed of 11m/s and installed at 85 meters high

The plant is installed in the municipality of Beberibe, Ceará, 102 km east of State capital Fortaleza.

The elevating substation is located in the wind power plant itself, with two 20 MVA and 15 MVA – 34.5 KV/69 kV transformers, making up Parajuru A and Parajuru B power buses, through which the wind turbines are connected to Enel Concessionaire’s Distribution Grid.